Schedule
Construction Schedule is Subject to Change Pending Weather.

Week of January 28, 2008
Landscape maintenance.

Week of January 21, 2008
Landscape maintenance.

Week of January 14, 2008
Landscape maintenance.

Week of January 7, 2008
Landscape maintenance.

Week of December 31, 2007
Landscape maintenance.

Week of December 24, 2007
No work scheduled.

Week of December 17, 2007
Landscape maintenance.

Week of December 10, 2007
Landscape maintenance.

Week of December 3, 2007
No work is scheduled.

Week of November 19, 2007
Landscape maintenance.

Week of November 12, 2007
Landscape maintenance and electrical repairs.

Week of November 5, 2007
Landscape maintenance and establishment.

Week of October 29, 2007
Landscape maintenance and establishment.

Week of October 22, 2007
Landscape maintenance and establishment.

Week of October 15, 2007
Landscape maintenance and establishment. Caltrans safety inspections.

Week of October 8, 2007
Landscape maintenance and establishment. Caltrans safety inspections.

Week of October 1, 2007
Landscape maintenance and completion of LED signs at Northbound off-ramp.

Week of September 24, 2007
Completion of left turn signal at Kanan Road and Canwood. Installation of LED signs at Northbound off-ramp.

Week of September 17, 2007
No work scheduled.

Week of September 10, 2007
Signal work near the Interchange at Kanan Road and Canwood (Thursday – all day).

Week of September 4, 2007
Electrical work for signals and landscape maintenance.

Week of August 27, 2007
Night work installation of overhead signage.

Week of August 20, 2007
Landscape maintenance, overhead sign installation, LED signs on northbound offramp.

Week of August 13, 2007
Install pedestrian crosswalk signal head on Kanan Rd, striping, and preparation for overhead freeway sign on southbound offramp.

Week of August 6, 2007
Landscape maintenance.

Week of July 30, 2007
Landscape maintenance.

Week of July 23, 2007
Landscaping and electrical work.

Week of July 16, 2007
Electrical work on signals at southbound loop ramp and Kanan Rd/Roadside Dr. intersection and landscape work.

Week of July 9, 2007
Landscaping, electrical and signal work at Kanan Road/Roadside Drive, striping, signal work at Kanan Road/Canwood Street.

Week of July 2, 2007
Landscaping and irrigation, concrete repairs.

Week of June 25, 2007
Surface finish on concrete bridge; retaining walls, & tieback walls; clean up work; landscaping; ballard installation fire hydrant on Roadside Drive; water facilities clean up and painting.

Week of June 18, 2007
Landscape work (mulch); irrigation work (Kanan Road Median & Roadside Drive); sign installation throughout project; AT&T manhole raising (Kanan Road).

Week of June 11, 2007
Construction work includes electrical work, signal head installations, landscaping, and installation of signage.

Week of June 4, 2007
Construction work includes final phase of landscape work, electrical work, and rock blanket work (northbound exit), signal loops will be done on Kanan Road on the nights of June 6th & 7th (Traffic may be closed during the hours of 10:00 PM to 5:00 AM the evening of June 6th and 7th).

Week of May 28, 2007
All week: Landscaping, electrical work.
Thursday May 31, 2007 and Friday June 1, 2007: Signal loop installation.

Week of May 21, 2007
All week: Landscaping, electrical work, fencing to be replaced.
Tuesday May 22, 2007: installation of new signage and installation of channelizers.
Wednesday May 23, 2007: installation of new signage.

Week of May 14, 2007
Daytime work
Landscaping work is on-going during the day the entire week.
Traffic control will be in place to raise manholes on Kanan Road.
Channelizers will be placed at on-ramps at Kanan Road median.
Night work
Work on Rte 101 (NB) and (SB) with mainline highway being closed for this work. Only one direction will be closed at one time. This work is to install traffic loops.
Wednesday May 16, 2007 and possibly Thursday May 17, 2007 night work will be on SB and NB off-ramps for traffic loops.

May 7, 2007
Paving of Park & Ride Lot, striping work on Kanan Road (night time work), signal loops, traffic signal/electrical work, paving of Roadside Drive, sidewalk & concrete work/repairs, landscaping (irrigation & soil preparation).

April 30, 2007
Paving of Park & Ride Lot, striping work on Kanan Road (night time work), signal loops, traffic signal/electrical work, paving of Roadside Drive, sidewalk & concrete work/repairs, landscaping (irrigation & soil preparation).

April 23, 2007
Work along the new southbound loop ramp, rock blanket, Park & Ride (north side), SWPP maintenance, traffic signal connections


4/9/07 - Two Week Look-Ahead Schedule (PDF)
3/19/07 - Two Week Look-Ahead Schedule (PDF)
3/05/07 - Two Week Look-Ahead Schedule (PDF)
2/12/07 - Two Week Look-Ahead Schedule (PDF)
1/29/07 - Two Week Look-Ahead Schedule (PDF)
1/12/07 - Two Week Look-Ahead Schedule (PDF)
12/18/06 - Two Week Look-Ahead Schedule (PDF)
12/04/06 - Two Week Look-Ahead Schedule (PDF)
11/20/06 - Two Week Look-Ahead Schedule (PDF)
11/06/06 - Two Week Look-Ahead Schedule (PDF)
10/23/06 - Two Week Look-Ahead Schedule (PDF)
10/09/06 - Two Week Look-Ahead Schedule (PDF)
9/25/06 - Two Week Look-Ahead Schedule (PDF)
9/11/06 - Two Week Look-Ahead Schedule (PDF)
8/28/06 - Two Week Look-Ahead Schedule (PDF)
8/14/06 - Two Week Look-Ahead Schedule (PDF)
7/31/06 - Two Week Look-Ahead Schedule (PDF)
7/17/06 - Two Week Look-Ahead Schedule (PDF)
7/03/06 - Two Week Look-Ahead Schedule (PDF)
6/12/06 - Two Week Look-Ahead Schedule (PDF)
5/29/06 - Two Week Look-Ahead Schedule (PDF)
5/15/06 - Two Week Look-Ahead Schedule (PDF)
5/1/06 - Two Week Look-Ahead Schedule (PDF)
4/17/06 - Two Week Look-Ahead Schedule (PDF)
4/03/06 - Two Week Look-Ahead Schedule (PDF)
3/20/06 - Two Week Look-Ahead Schedule (PDF)
3/06/06 - Two Week Look-Ahead Schedule (PDF)
2/20/06 - Two Week Look-Ahead Schedule (PDF)


Phases of Project

Planning - COMPLETED

  • Project Study Report
  • Environment Documents
  • Project Report
  • Final Design/Right-of-way Acquisition


Phase I: New Canwood Street Realignment - COMPLETED
  • Relocation of Canwood Street


Phase II: Utility Relocation/Undergrounding - COMPLETED
Expected Completion mid-2006
  • Relocation of Sewer & Water Utilities
  • Relocation of Electric, cable, telephone
  • Relocation of Gas line


Phase III: Interchange Construction - UNDERWAY
Expected Completion early 2007
  • Reconstruction of Freeway Ramps and Signals
  • Signage, Striping
  • New Walls, Irrigation, Landscaping, and Drainage